Line 6: Line 6:
 
*2+ for each table in the classroom (6 tables?)  
 
*2+ for each table in the classroom (6 tables?)  
 
*2+ more near the presenter's table in the classroom
 
*2+ more near the presenter's table in the classroom
 +
 +
*outlets for A/C units/exhaust fans
  
 
this adds up to:  
 
this adds up to:  
Line 17: Line 19:
  
 
*kitchen light (switch by the sink) doesn't work
 
*kitchen light (switch by the sink) doesn't work
 
+
*server room needs a light switch instead of plug hookup
 +
*light switches need to be labeled
 
== Breaker box ==
 
== Breaker box ==
 
Do we still need our own subpanel? If so, what's the cost?
 
Do we still need our own subpanel? If so, what's the cost?
  
 
(I believe it'll save money in the longrun since we won't haver to run shielded cable as far)
 
(I believe it'll save money in the longrun since we won't haver to run shielded cable as far)

Revision as of 19:44, 12 September 2011

Where we need outlets and how many:

  • 2+ in the kitchen for microwave and toaster/etc
    • Plus a 220v for a stove when we get one
  • 2+ for each couch in the lounge (6 couches?)
  • 2+ for each table in the classroom (6 tables?)
  • 2+ more near the presenter's table in the classroom
  • outlets for A/C units/exhaust fans

this adds up to:

  • 14x 2+ outlet boxes enough shielded conduit to make runs to all these


I don't think the workbench needs any more right away (we have good coverage there with extension cords right now) and the workshop area can also wait.


Other electrical work needed:

  • kitchen light (switch by the sink) doesn't work
  • server room needs a light switch instead of plug hookup
  • light switches need to be labeled

Breaker box

Do we still need our own subpanel? If so, what's the cost?

(I believe it'll save money in the longrun since we won't haver to run shielded cable as far)